You are on page 1of 28

UPAL SINHA SUNOY KR.

BENTE PRITAM SINHA ROY SAYANTAN BHATTACHARJEE SHOUVIK MUKHERJEE

GENERATOR:
SOURCE OF ELECTRICAL ENERGY

TRANSMISSIO N LINE:
TRANSMITTING POWER

LOAD:

CONSUMING POWER

Limit = 100 MVA 25.0 MW 100.0 MW Bus A

25% 100%

Rest of Electric System

Limit = 100 MVA

175.00 MW

300.0 MW
8

FAIR AND NON-DISCRIMINATORY ECONOMICALLY EFFICIENT TRANSPARENT AND NON-AMBIGUOUS FEASIBLE COMPATIBLE WITH MARKET

10

NET TRANSFER CAPACITY(NTC)


Represents the best estimate limit for physical electricity transfer between two areas.

AVAILABLE TRANSFER CAPACITY(ATC)


Transfer capacity remaining between two interconnected areas for further commercial activity over and above already committed uses of the transmission networks.

11

CURTAILMENT BASED ON PUBLISHED NTCs AUCTIONING MARKET SPLITTING REDISPATCHING

12

When NTCs are used as an upper limit of the available transmission capacity, no further capacity can be allocated by TSOs once the limit is reached. Then the method requires that a mechanism to define the priority for using NTCs be implemented. ADVANTAGE: No additional costs are incurred, and thus there is no allocation or cost allocation mechanism. DRAWBACKS: Curtailment of transactions based on NTCs publication does not convey any economic incentive. It does not provide incentives to TSOs, generators, distributors, traders and therefore does not promote efficient trade.

13

The auctioning method is efficient regarding competition :bids reflect exactly the real market value as perceived by the participants, the highest priority for access being granted to the one who is ready to pay the highest price. ADVANTAGE: The auctioning system allows TSOs to handle constraints for cross-border trading, without providing any physical information except NTC. DRAWBACKS: Auctioning raises a transmission risk on long or mid-term bilateral contracts (there is no guarantee that they will be accepted every day)

14

This method consists of splitting a power exchange (PEX) into geographical bid areas Each area has its own pool price : areas downstream of a congestion will have a higher pool price, areas upstream of a congestion will have a lower pool price When the price-demand effect is observed, demand decreases as price increases ADVANTAGE: On a long-term basis, customers may react to high prices in congested areas by substituting other forms of energy to electricity DRAWBACKS: It is not feasible on a large scale

15

Redispatch effectively allows extending trade through reoptimisation despite physical boundaries, till there is no generation possibilities left to redispatch ADVANTAGE: The advantage of publishing likely congestion costs in advance is that it allows good visibility of these issues to all participants. DRAWBACKS: Preparing the above cost curve places significant computational difficulties on the TSOs

16

17

It is assumed that the market knows market limits (NTCs published by TSOs). This situation could be supported by any number of contracts, but G2, G3 and G4 between them can only contract up to 280 MW (2 x 100 MW + 2 x 40 MW NTC). The access to B-A and B-C interconnectors is allocated according to chosen priority rules.

18

An efficient market is assumed (the market has enough information as to adjust generation with respect of NTCs) with : G1 200 MW G2 200 MW G3 80 MW G4 0 MW G5 20 MW This situation could be supported by any number of contracts. Assuming that G2 has contracted with D2 and D3, G3 and G4 could be competing in the auction for capacity between B and A, and between B and C. G3 could obtain 80 MW of capacity in this auction.

19

20

21

22

LMP LOCAL MARGINAL PRICES TUT TRANSMISSION USAGE TARIFF LMP lossless = EP + CR LMP loss= EP + CR + LC EP ENERGY PRICE CR CONGESTION REVENUE LC TRANSMISSION LOSSES COST LMP-TUT = EP + CR + LC + TUT

23

24

Format-I National

/________Regional Load Despatch Centre

Total Transfer Capability for mmmm ,yyyy Issue Date: Issue Time: Revision No.
Corridor/ Date Control Area Time Period Reliabili Total ty Available Transfer Margin Transfer Capabili (RM) ty (TTC) Capability (ATC)

Remarks:

25

Format II

National/_________Regional Load Despatch Centre


Congestion Monitoring Display dd/mm/yyyy, hh:mm TTC ATC Corridor/ Control Area Actual

26

APPLICABILITY OF CONGESTION CHARGE


Format V National/_________Regional

Load Despatch Centre


Date: dd/mm/yy Time of Issue:

Notice Number: (LDC/RLDC)/yyyy/mm/.


hh:mm To

NOTICE FOR LIFTING OF CONGESTION CHARGE Congestion charge on Unscheduled Interchange (UI) energy that was applicable w.e.f hh:mm of dd/mm/yyyy vide notice umber.... issued at hh:mm of dd/mm/yyyy would be lifted w.e.f time block no. (hh:mm) of dd/mm/yyyy. Shift Charge Manager

27

28

You might also like